Sichuan Huisheng New Energy Co., Ltd.'s 100,000 tons per year biodiesel instrument electrical automation project
Project Background

> Sichuan Huisheng New Energy Co., Ltd.'s 100,000-ton annual biodiesel project is located in the Jinxiang Chemical Industry Park in Meishan City, and the construction nature is new construction. Sichuan Huisheng New Energy Co., Ltd. is a professional business enterprise that mainly produces biodiesel products. The project construction occupies a pivotal position in the new energy industry in Meishan City, which puts it in a favorable position in the market competition, ensures the quality of the products, lays the foundation for creating a brand, and promotes the company to enhance its core competitiveness.

Configuration Scheme
● Controller AS410Smart controller + ET200M Profibus-DP

● SIMATIC PCS7 V8.0

● I/O points: 2000 points

Project Highlights
● As the biodiesel project with the largest design capacity at present, Gaoda Technology has improved the complete set of electrical automation and installation integrated solutions, applied Siemens PCS7 fully integrated digital concept, integrated field equipment control, and a large number of automated and intelligent program applications, reducing the number of on-site inspection personnel and ensuring the high-quality operation of the production line.